As we all know Primavera is an hour Planner: it calculates everything in hours. All other time units shown (days, weeks, months, years) are just a calculation. This calculation is based on how many hours we define as a day, week, month, year. And we define that in two different locations in Primavera: Option A …
A. The Problem Let’s consider the scenario that we just finalized our programme in Primavera and that the whole programme uses calendars with 8 working hours per day. Consider it as a real world programme, big, 2-3 different calendars used (5day, 6day, 7day) and with all kind of relationships [FS, SS, FF (and SF if …